Upgrading the power supply of an industrial unit: how it's done, step by step
A new machine, an extra line or a bigger compressor. What a power upgrade involves and how to stop the paperwork holding up your project.

The new machine arrives and, suddenly, the installation has reached its limit. A power upgrade is a routine procedure, but it pays to do it in an orderly way so it doesn't delay commissioning.
First: how much power you really need
It isn't a matter of adding up the power ratings of all the machines. You have to consider which equipment runs at the same time, motor starting currents and foreseeable growth. A good calculation avoids falling short and also overpaying on the power charge.
Second: ask the distribution company for its conditions early
With an approximate power figure, ask the distribution company for the technical conditions for the upgrade. Its response determines the service connection, the connecting installation and even the supply voltage. If the local network has capacity, the process is quick; if not, the distribution company may require works on its network. In addition, supplies of more than 50 kW cannot be provided at low voltage unless agreed with the distribution company (Real Decreto 1955/2000, artículo 46): it may propose a high-voltage supply, which normally means a transformer substation. That is why it is worth making this enquiry at the start, before the machine arrives.
Third: review the existing installation
More power means more current. The service connection, the main supply line, the panel and the protective devices have to be ready. Sometimes adjusting the protective devices is enough; other times the connection installation or the main switchboard itself has to be upgraded.
Fourth: the documentation
Once the distribution company has responded, the technical documentation (technical report or project, depending on the power and the type of installation) and the installation certificate are finalised. If the installation falls within the cases covered by ITC-BT-05, for example an industrial installation with a project of more than 100 kW, a significant upgrade also needs an initial inspection by an approved inspection body before the increased supply is connected.
Fifth: commissioning
Once the power is granted, the new equipment is connected, the protective devices are adjusted and everything is checked under load.
Our advice
Plan the upgrade at the same time as you purchase the machinery and consult the distribution company from day one. At Lamper we handle the whole process: calculations, upgrading the installation, documentation and liaising with the distribution company.