Which industrial units, premises and shops need to pass the periodic electrical inspection (OCA), and how often?

In short

If your industrial unit, premises or shop needed an initial inspection (for example, an industrial facility with a design of more than 100 kW or a public assembly venue), it must pass a periodic inspection every 5 years. It is carried out by an accredited control body (OCA), not by your installation company. Below are the cases set out in the regulation.

REBT · ITC-BT-05
Every 5 yearsEvery low-voltage installation that needed an initial inspection must repeat it every 5 years.
Every 10 years in large residential buildingsThe communal installations of a residential building are inspected every 10 years if the building's total installed power is more than 100 kW.
Carried out by a control bodyThe regulatory inspection is carried out by an accredited control body (OCA). The installation company may attend, but does not sign it.
Three possible resultsThe certificate is issued as favourable, conditional (there is a serious defect, or a minor defect from the previous inspection that has not been corrected) or unfavourable (there is a very serious defect).
Maximum 6 months to correctIf the result is conditional, the period for correcting defects cannot exceed 6 months. If they are not corrected, the certificate becomes unfavourable and is sent to the Administration.
The owner is the one who requests itThe obligation lies with the owner of the installation: whoever is named as the owner on the installation certificate. This is usually the company occupying the premises or the industrial unit, even if it is rented. For common areas, it is the residents' association. The owner is the one who requests the inspection from the inspection body.

Who does it affect?

  • Industrial installations (industries, workshops, factories) that required an electrical design project and have more than 100 kW of installed power.
  • Premises open to the public (those listed in ITC-BT-28). Always, regardless of size, including among others: bars, cafés, restaurants, hotels, cinemas, theatres, nightclubs, hospitals, outpatient clinics and sanatoriums, care homes (residences for older people), nurseries, enclosed and covered car parks for more than 5 vehicles and common areas of shopping centres.
  • Shops, offices serving the public, gyms, academies, medical practices, exhibition halls or student residences, when the expected occupancy exceeds 50 people. Occupancy is calculated as 1 person per 0.8 m² of usable floor area, not counting corridors, lobbies and toilets.
  • Any other premises with capacity for more than 100 people. Also premises where evacuation is difficult (those classified under conditions BD2, BD3 or BD4).
  • Premises with a class I fire or explosion risk (where there are or may be gases, vapours or mists in sufficient quantity to form explosive or flammable atmospheres, or flammable liquids), except car parks with fewer than 25 spaces. Note: that small car park is only excluded on this ground. If it is enclosed and covered for more than 5 vehicles, it is included as premises open to the public.
  • Wet locations (floors, walls or ceilings soaked with water, with large droplets or condensation for long periods, such as laundries or dry cleaners; also outdoor installations) with more than 25 kW.
  • Swimming pools with more than 10 kW installed.
  • Operating theatres and procedure rooms.
  • Outdoor lighting (car parks, roads, façades, grounds) with more than 5 kW.
  • Electric vehicle charging installations that required a design project. Those over 50 kW, outdoor ones over 10 kW and all DC rapid charging installations (mode 4) require one. A standard charging point in the existing garage of a residential building does not require a project, unless it falls into one of those cases.
  • Common installations in residential buildings when the building's total installed power exceeds 100 kW: in this case, every 10 years.

What is not included (and is often confused)

  • The installer's verification is not the OCA inspection. When an installation is finished, the installation company verifies it before putting it into service. That is something different and does not replace the inspection by the inspection body.
  • The interior installation of a home does not have a periodic inspection just because it is a home (unless it includes something on the list, such as a swimming pool of more than 10 kW). The building's common areas do have one, every 10 years, if the building's total installed power exceeds 100 kW.
  • An office not open to the public or a warehouse with capacity for 100 people or fewer (and without difficult evacuation conditions BD2, BD3 or BD4), or a small shop (occupancy of 50 people or fewer), are not premises open to the public on that basis. They may need an inspection for another reason on the list (for example, power, wet location or explosion risk).
  • An industrial unit of 100 kW or less is not included on power grounds. It is included if it has, for example, an area with a class I explosion risk.
  • Passing the inspection does not remove the need for maintenance. The owner must keep the installation in good condition at all times, and any modification must be carried out by an installation company.
Example

Example: a 150 kW industrial unit in the Vallès

Fictitious example. A machining workshop in an industrial unit in the Vallès has 150 kW installed and its installation was carried out with a design project, so it passed an initial inspection. Five years later, the periodic inspection is due. The inspection body finds a serious defect: there is no continuity in a protective conductor (the green-and-yellow cable that connects exposed conductive parts to earth) in a secondary panel. The certificate is issued as conditional, with a correction period that cannot exceed 6 months. The installation company repairs it, the inspection body checks it and the rating becomes favourable. If it had not been corrected in time, the certificate would have become unfavourable and been sent to the authorities.

What you need to do

  1. Check whether your installation is on the list: installed power, type of premises, expected occupancy, and wet areas or areas with a risk of explosion.
  2. Find the certificate from the last inspection (initial or periodic) and note its date. The 5 years (or 10 years for communal areas of residential buildings) are counted from that date. If your installation is on the list and has never been inspected by an inspection body, don't wait: request an inspection as soon as possible, because the initial inspection was mandatory before it was put into service.
  3. Request the inspection from an inspection body accredited for low voltage. Have the installation documentation to hand (installation certificate, design or technical report, diagrams).
  4. If defects are found, have them corrected by an installation company and don't work on the installation yourself.
  5. If the result is conditional, correct the defects within the period you are given (6 months at most) and ask the inspection body to check them.
  6. Keep the favourable certificate and note the date of the next inspection.
If you don't comply. If the result is unfavourable, or conditional and not corrected in time, the inspection body sends the unfavourable certificate to the regional government. Under the Industry Act (Law 21/1992), failing to correct the defects found in an inspection within the deadline is a minor offence, unless those defects are in themselves a serious or very serious offence. If the rating becomes unfavourable and the installation is still used, it may be a serious offence: keeping an installation in operation without having passed the mandatory inspection. In Catalonia, Law 9/2014 on industrial safety also applies. It classes failure by the owner to arrange the periodic inspection, when it is mandatory, as a serious offence. And in Catalonia, if there is an imminent danger, the inspection body can order the installation to be taken out of operation as a precautionary measure. Fines depend on the case and are set by the authorities.

FAQ

Who carries out the periodic electrical inspection?

An accredited low-voltage control body (OCA). The installation company may be present, but the inspection and the certificate belong to the control body. In Catalonia, control bodies also handle recording the result of periodic inspections in the Registry of Industrial Safety Technical Installations of Catalonia.

Are my shop premises classed as a public assembly venue?

A retail establishment is if its expected occupancy exceeds 50 people. This is calculated at 1 person per 0.8 m² of usable floor area, excluding corridors, lobbies and toilets. Bars, cafés and restaurants always are, whatever their size.

What is the difference between favourable, conditional and unfavourable?

Favourable: there are no serious or very serious defects; minor defects are recorded and must be corrected before the next inspection. Conditional: there is at least one serious defect, or a minor defect from the previous inspection that has not been corrected; there is a maximum period of 6 months. Unfavourable: there is at least one very serious defect and the certificate is sent to the Administration.

Does the check my electrician carries out count as an inspection?

No. The installation company verifies the installation before it is put into service and can carry out maintenance, but the initial and periodic inspections must be carried out by a control body.

Does a residents' association have to pass an inspection?

Yes, if the total installed power of the residential building exceeds 100 kW: the communal installations are inspected every 10 years. What counts is the power of the whole building, not just the communal areas. If the building has an enclosed, covered car park for more than 5 vehicles, that part is classed as a public assembly venue and is inspected every 5 years.

The original regulation

This explanation summarises the regulation in plain language. The legally binding text is the official one:

Reviewed on 27 November 2026. Regulations change: if you spot something out of date, let us know.

Further reading

Talk to a technician

Informative content: it does not replace the official text of the regulation or the judgement of a qualified professional or the competent authorities.